ROAD CONSTRUCTION UPDATES
October 22, 2025

Bike and Pedestrian Trail Update

October 22, 2025

CONTACT: City of Batesville, Mayor’s Office
Andrea Wade, [email protected], 812-933-6100

BATESVILLE, Ind. Bike and Pedestrian Trail Expansion Update

Crews are completing their work on the east side of State Road 229, between Hillcrest Avenue and State Road 46 and will be switching the traffic pattern to the west side on Monday, October 27. Traffic remains restricted, as it has been since August, to southbound only. This phase of the project is scheduled to be completed by the end of November 2025.
Your patience is appreciated as we move toward creating safer and more connected pathways for our residents to use and enjoy.

###